NEW DELHI, November 27: Jammu and Kashmir Minister for Power Development Department Ali Mohammad Sagar has sought a dedicated financial package from the Centre to modernise the Union Territory’s power sector, strengthen its infrastructure and address the widening gap between electricity demand and supply during winter.
Sagar made the demand during the State Ministers’ Conference on Power in New Delhi, chaired by Union Power Minister Manohar Lal. He also submitted a memorandum outlining the sector’s requirements, including financial assistance for distribution and transmission networks, hydropower development, energy storage and disaster-resilient infrastructure.
Highlighting the challenges faced by Jammu and Kashmir, Sagar said mountainous terrain, scattered habitations, remote locations and extreme weather conditions made the development and maintenance of power infrastructure particularly difficult. He said snowfall, avalanches, landslides, cloudbursts and flash floods frequently disrupted electricity networks, while demand increased during winter when hydropower generation declined.
The Minister said revenue realisation by Jammu Power Distribution Corporation Limited (JPDCL) and Kashmir Power Distribution Corporation Limited (KPDCL) had increased from around ₹3,060 crore in 2021–22 to ₹5,290 crore in 2025–26, registering growth of nearly 73 per cent.
He also cited a decline in aggregate technical and commercial (AT&C) losses, from 49.82 per cent to 27.13 per cent in JPDCL and from 65.61 per cent to 33 per cent in KPDCL.
Under the Revamped Distribution Sector Scheme (RDSS), 14.07 lakh smart meters have been sanctioned, of which around 12.25 lakh had been installed by November 19, 2026. Distribution strengthening and loss-reduction works worth ₹4,708.52 crore have also been sanctioned.
Sagar sought further Central assistance for replacing ageing and overloaded transformers, augmenting 33/11 kV infrastructure, installing additional substations and strengthening low-tension networks. He also called for underground and insulated cabling in vulnerable areas and dedicated enforcement wings to curb power theft.
On the winter supply situation, the Minister said peak demand during the previous winter had reached around 3,362 MW, including 1,456 MW in Jammu and 1,906 MW in Kashmir. The anticipated restricted demand for winter 2026–27 is around 3,450 MW, with the estimated supply gap ranging between 600 MW and 1,300 MW.
He urged the Centre to provide additional unallocated power, ensure predictable allocations and continue or enhance the additional 329 MW allocation for December 2026 to February 2027. He also sought support for affordable long-term power procurement and banking arrangements with neighbouring states, including Punjab and Uttar Pradesh.
On hydropower, Sagar said Jammu and Kashmir had an estimated potential of 14,635 MW, of which around 3,540 MW had been harnessed. He referred to the ongoing Pakal Dul, Kiru, Kwar and Ratle projects, with a combined capacity of approximately 3,563.5 MW, and said the government aimed to increase installed hydropower capacity to around 10,975.65 MW by 2035.
He sought Central grants, concessional financing and viability gap funding to accelerate hydropower projects, undertake geological investigations and prepare detailed project reports. He also highlighted the proposed Jammu and Kashmir Hydro Power Policy 2026 as a measure to encourage investment in the sector.
The Minister proposed developing 250 MW/1,000 MWh of Battery Energy Storage System capacity over three years and scaling it up to 1,000 MW/4,000 MWh over five years, up to 2031, to manage peak demand and integrate renewable energy.
On transmission infrastructure, he highlighted the Jammu and Kashmir Power Transmission Corporation Limited’s transformation capacity of around 12,875 MVA, with another 3,766 MVA in the pipeline. He sought support for new transmission lines, grid substations, transformer augmentation and modern digital substations.
Sagar also proposed a dedicated Himalayan Power Infrastructure Resilience Programme to protect electricity infrastructure against natural disasters. He said seven Emergency Restoration System (ERS) units had been procured for Jammu and sought 15 additional units for Jammu and 10 for Kashmir.
Other proposals included investment in smart-grid technologies, cybersecurity and specialised training, besides establishing two dedicated power training colleges, one each in the Jammu and Kashmir divisions.
Seeking a dedicated Jammu and Kashmir Power Sector Development and Modernisation Package, the Minister proposed a combination of grants, concessional loans, viability gap funding and project-based assistance. He also called for a joint working group comprising representatives of the Centre and the UT administration to examine the proposals and facilitate their time-bound implementation.
He said reliable and affordable electricity was essential for industrial growth, tourism, horticulture, healthcare and other economic activities in Jammu and Kashmir.